Detailed programme

Phase

Section

Start date

Duration

Expected disruption

Plans

A

Steedman Street junction with Hampton Street (western footpath)

1 July 2019

3 weeks

Temporary traffic signals, parking spaces to be suspended

 

B

Steedman Street, western footpath

22 July 2019

3 weeks

Temporary traffic signals, parking spaces suspended

 

C

Entrance to Marlborough Close preliminary works

12 August 2019

1 week

No access in or out of garages

 

D

Entrance to Marlborough Close

19 August 2019

2 weeks

No access in or out of Marlborough Close

 

E

Steedman Street, southern footway

2 September 2019

8 weeks

Vehicle access disruptions

 

F

Steedman Street, northern footway

October 2019

TBC

Vehicle access disruptions

 

G

Hampton Street junction with Wollaston Close

October 2019

TBC

Road closure at Walworth Road, Hampton Street becomes two-way

 

H

Steedman Street junction with Walworth Road

January 2020

TBC

Temporary traffic signals, parking spaces suspended

 

I

Carriageway works (raised junctions)

February 2020

TBC

Temporary traffic signals, road closures, parking spaces suspended

 

 

Note: all of the above is subject to change. We will endeavor to update the website as well as having an approachable presence on site. Further communication may be sent via post.