Hampton Street and Steedman Street improvements
Detailed programme
Phase |
Section |
Start date |
Duration |
Expected disruption |
Plans |
---|---|---|---|---|---|
A |
Steedman Street junction with Hampton Street (western footpath) |
1 July 2019 |
3 weeks |
Temporary traffic signals, parking spaces to be suspended |
|
B |
Steedman Street, western footpath |
22 July 2019 |
3 weeks |
Temporary traffic signals, parking spaces suspended |
|
C |
Entrance to Marlborough Close preliminary works |
12 August 2019 |
1 week |
No access in or out of garages |
|
D |
Entrance to Marlborough Close |
19 August 2019 |
2 weeks |
No access in or out of Marlborough Close |
|
E |
Steedman Street, southern footway |
2 September 2019 |
8 weeks |
Vehicle access disruptions |
|
F |
Steedman Street, northern footway |
October 2019 |
TBC |
Vehicle access disruptions |
|
G |
Hampton Street junction with Wollaston Close |
October 2019 |
TBC |
Road closure at Walworth Road, Hampton Street becomes two-way |
|
H |
Steedman Street junction with Walworth Road |
January 2020 |
TBC |
Temporary traffic signals, parking spaces suspended |
|
I |
Carriageway works (raised junctions) |
February 2020 |
TBC |
Temporary traffic signals, road closures, parking spaces suspended |
|
|
Note: all of the above is subject to change. We will endeavor to update the website as well as having an approachable presence on site. Further communication may be sent via post. |