Dulwich Village - Streets for people

Construction progress update – August 2024

Dulwich Overview Map
View a plan of the progress update

 

View the latest phasing of construction (PDF, 1.9mb).

Works completed in August

  • more expansive footway adjacent to Dulwich Village C of E Infants' School, on Dulwich Village and Turney Road - completed
  • rain garden along Dulwich Village - completed
  • installation of two tree pits at the new public square area on Calton Avenue – completed
  • public space adjacent to the shops on Calton Avenue – started
Newly laid footway in Dulwich
New widened footway in Dulwich

View the independent assessment report regarding the removal of the guardrail (PDF, 3.8mb).

Works planned for September

  • public space adjacent to the shops on Calton Avenue - to be completed mid-September
  • laying of granite setts on the cycle track
  • install green spaces to support biodiversity
  • completion of all works on Turney Road and Dulwich Village - south of Turney Road  
  • sustainable urban design works on Calton Avenue

How the works will impact residents

Bus stop on a leafy quiet road
Bus stop suspension on Dulwich Village
  • bus stop suspension on Dulwich Village, adjacent to Burial ground - from 3 to 9 September
  • Cyclists diversion – see diversion route (PDF, 520kb)
  • temporary pedestrian crossing  
  • access to be maintained at all times to local shops

 

 

 