Cycle 35

As part of the TfL Cycleway programme, we carried out a feasibility study in 2017 for C35 Bermondsey to Catford. The section from Bermondsey to Peckham was implemented in 2020. We're now planning to link up Peckham Rye Gyratory to Brockley Mews via this route.

C35 is divided into two sections:

  • between Nunhead Lane and Stuart Road
  • between Stuart Road and Brockley Mews

The section between Nunhead Lane and Stuart Road is in the detailed design phase.

The section between Stuart Road and Brockley Mews is in the outline design phase.

Timeline between Nunhead Lane and Stuart Road

  • Scoping design – completed
  • Outline design – completed
  • Consultation – completed
  • Outline design amendments & detailed design – June 2024 to October 2024
  • Implementation – TBC

Consultation

It was consulted in Autumn 2023. See here for a record of the decision:

Issue details - C35 segregated cycleway on Peckham Rye - Southwark Council

Post consultation some design changes were made, in response to feedback received.

Timeline between Stuart Road and Brockley Mews

  • Scoping design – completed
  • Outline design – June 2024 to September 2024
  • Consultation – TBC
  • Detailed design – TBC (subjects to Cabinet Member decision)
  • Implementation – TBC

If you have any questions, email highways@southwark.gov.uk.